Water Projects
PROMOTER: Namibia Water Corporation
Water scarcity remains one of the most pressing environmental issues of the century. The lack of fresh water resources to meet consumption demand affects every continent. Namibia is a semi-arid country, and the rainfall patterns have mostly been erratic. Projects to the value of N$ 3,3 billion are earmarked to address these deepened concerns. These include bulk water projects to the tune of N$ 3,1 billion, reclamation projects to the value of N$450 million and rural water projects amounting to N$ 1,5 billion respectively. In addition, grants have been secured to aid cross-cutting projects in capacity development through training.
LOCATION: All Regions
OUTLINE OF PROJECTS
Project Name | Estimated Total Cost (N$) incl VAT | Estimated Requirement FY2018/19 (N$) incl VAT | Estimated Requirement FY2019/20 (N$) incl VAT | Estimated Requirement FY2020/21 (N$) incl VAT | Estimated Requirement FY2021/2022 (N$) incl VAT | Estimated Requirement FY2022/23+ (N$) incl VAT |
Completion of CAN short term projects | ||||||
Kombat & Berg Aukas power supply upgrade | 9,800,000 | 2,300,000 | 7,500,000 | |||
Omatako to Von Bach pump stations refurbishment |
9,500,000 |
9,500,000 |
||||
Subtotal Phase 1 Projects |
19,300,000 |
11,800,000 |
7,500,000 |
|||
NamWater Emergency Projects | ||||||
Central Area of Namibia
(CAN) |
||||||
Abenab borehole
development and linking with ENWC |
644,200,000 |
17,100,000 |
6,100,000 |
192,000,000 |
429,000,000 |
|
- drilling of boreholes, EIA, preliminary design |
21,600,000 |
17,100,000 |
4,500,000 |
|||
- final design and
procurement |
1,600,000 |
1,600,000 |
||||
- construction |
621,000,000 |
192,000,000 |
429,000,000 |
|||
Central Northern Area
(CAN) |
||||||
Oshakati Purification
Plant Extension |
554,300,000 |
20,000,000 |
240,000,000 |
240,000,000 |
54,300,000 |
|
- EIA, process and
preliminary design |
20,000,000 |
20,000,000 |
||||
- final design,
procurement andconstruction |
534,300,000 |
240,000,000 |
240,000,000 |
54,300,000 |
||
Ohangwena No 2 Well
Field |
24,400,000 |
600,000 |
700,000 |
21,800,000 |
1,300,000 |
|
- EIA, process and
preliminary design |
1,300,000 |
600,000 |
700,000 |
|||
- final design and
procurement |
23,100,000 |
21,800,000 |
1,300,000 |
|||
Central Coastal Area
(CCA) |
||||||
Kuiseb Collector 2
SchwarzekuppeSwakopmund Phases 2 and 3 |
418,000,000 |
200,000,000 |
200,000,000 |
18,000,000 |
||
- final design,
procurement and construction |
418,000,000 |
200,000,000 |
200,000,000 |
18,000,000 |
||
Omdel-Wlotzkasbaken
pipeline replacement |
240,000,000 |
|
110,000,000 | 130,000,000 | ||
- final design,
procurement and construction |
240,000,000 |
110,000,000 |
130,000,000 |
|||
Rundu Urban Area
(RUA) |
||||||
Rundu Purification Plant
Extension |
679,000,000 | 35,000,000 | 288,000,000 | 288,000,000 | 68,000,000 | |
- EIA, process and preliminary design |
35,000,000 |
35,000,000 |
||||
- final design,
procurement and construction |
644,000,000 |
288,000,000 |
288,000,000 |
68,000,000 |
||
Subtotal NamWater Emergency Projects |
2,559,900,000 |
55,600,000 |
545,800,000 |
755,900,000 |
625,600,000 |
577,000,000 |
City of Windhoek
Emergency Projects |
||||||
Gammams Reclamation
Extension |
515,000,000 |
7,500,000 |
7,500,000 |
220,000,000 |
220,000,000 |
60,000,000 |
- pilot plant |
15,000,000 | 7,500,000 | 7,500,000 | |||
- detail design, procurement and construction | 500,000,000 | 220,000,000 | 220,000,000 | 60,000,000 | ||
Subtotal City of Windhoek Emergency Projects | 515,000,000 | 7,500,000 | 7,500,000 | 220,000,000 | 220,000,000 | 60,000,000 |
TOTAL FOR ALL PROJECTS |
3,094,200,000 |
74,900,000 |
560,800,000 |
975,900,000 |
845,600,000 |
637,000,000 |
TOTAL INVESTMENT:
Programme budget amounts to N$3,3 billion
IMPLEMENTATION PERIOD:
5 Years
CONTACT DETAILS:
Ms. Maria Amakali
Director: Directorate of Water Resource Management
Ministry of Agriculture, Water and Forestry
Tel: +264 61 208 7161
Mobile: +264 81 290 0823
Email: This email address is being protected from spambots. You need JavaScript enabled to view it.
Ms. Kadiva Hamutumwa
Chief Strategy Officer & New Business Development
Namibia Water Corporation
Tel: +264 61 71 2159
Mobile: +264 81 122 2869
Email: This email address is being protected from spambots. You need JavaScript enabled to view it.